Technical Office Engineer Interview Questions
Somewhere in a technical office interview, someone slides a slab plan across the table and asks you to take off the concrete and the rebar. They are not checking your arithmetic. They want to know whether you deduct the stair opening, where your wastage figure came from, and whether the quantity is for the purchase order or for the valuation, because those are two different numbers and a contractor who confuses them loses money twice.
That is the difference between this page and the general civil engineer page. That one covers the broad technical interview: concrete, reinforcement, site. This one is for the desk side of the project — documents, quantities, submittals, coordination, and money on paper. The person across the table is usually a technical office manager or a project manager, and the question underneath everything they ask is whether you will protect the company's position in writing.
It assumes the setting a technical office usually works in: approvals that run through a consultant, a contract that may well be a FIDIC form, and a quantity surveyor checking every number you send out.

Try the first technical office engineer interview question free with AI coach Maya
Here's a slab. Take off the concrete and the rebar.
No card · the full interview is $10, once
Take the whole set with you
All 34 questions as a PDF you can take into the interview. Free account.
The PDF for this role is not built yet.
Generated from this page. Nothing on this page is hidden from you — the account is for the file.
Start here — the five most asked
In the order the sources put them. If you only have twenty minutes, spend them on these.
- What does a technical office engineer actually do all day?
- Why the technical office and not site?
- Walk me through the contract documents on your last project. What wins when they conflict?
- Here's a slab. Take off the concrete and the rebar.
- Which method of measurement is your BoQ written to, and why should I care?
The phone screen
A recruiter filtering, not evaluating. Answer these quickly and get to the part that decides.
These two pages teach the frame. This page gives you the version that fits your field — read them together.
The opening ten minutes
All levels
These sound like warm-up questions. They are where the panel decides whether you have actually sat in a technical office or read a job description of one, so answer them with the job, not with adjectives.
What does a technical office engineer actually do all day?Show the answer guide
Describe a day, not a definition. Morning: check the RFI log for what came back overnight and what is about to go overdue. Then a batch of shop drawings to check before they go to the consultant, a take-off for an item the valuation needs, a response sheet for consultant comments on a submittal. Somewhere in the afternoon the site calls to ask whether the drawing they are holding is the current revision.
That last call is the job. The technical office is the one place on the project that is supposed to know which version of every document is live today.
Why the technical office and not site?Show the answer guide
They are checking you will not ask for a transfer to site in six months. Tie your answer to the work itself — documents turn into money here — and say you still want regular site time, because an office engineer who has never stood at a pour does not understand why site is shouting.
Walk me through the contract documents on your last project. What wins when they conflict?Show the answer guide
List them: the agreement, general and particular conditions, specification, drawings, bill of quantities, plus addenda and agreed correspondence.
Then the part that separates people. The order of precedence is not folklore you memorise; it is written in the contract. "The contract sets it, and reading that clause is the first thing I do on a new job" is the right answer. "Specs always beat drawings" tells the panel you have never opened one.
The technical sit-down
Where it stops being about your CV. You either know these or you don't — and bluffing fails on the follow-up.
The take-off test and the bill
Entry – mid
Graduates get tested hardest here, because quantities are often the first thing a new technical office engineer is handed. Expect a printed drawing and a calculator, or a laptop with Excel and sometimes an AutoCAD file.
Experienced candidates get the same questions with a sharper edge: not "what is the volume" but "which rules is that volume measured to".
Here's a slab. Take off the concrete and the rebar.Show the answer guide
The number at the bottom matters less than the sheet above it. Lay it out the way a real take-off sheet looks: element, drawing reference, dimensions, number, result, and a deductions column. Talk while you work. When you deduct the stair opening, say why; when you leave the small drainage openings in, say why that too.
Then ask the question the interviewer is waiting for: what is this quantity for? A purchase quantity includes laps and wastage because you pay for them. A valuation quantity follows whatever method of measurement the contract names. Ask which one before you write the final figure, and you will have answered the hardest part of the test without being asked.
One candidate's version
The slab was 18 by 12 at 200 thick, so 43.2 cubic metres gross. I took out the stair void, 3 by 5, which left 40.2, and I left the floor-drain openings in because they were tiny. Rebar I did by weight from the bar schedule. Then I said: if this goes in a valuation, it's measured to whatever the contract says; if it's for ordering steel, I'd add wastage and I'd want to know the supplier's stock lengths first.
His figures were the easy part. What made it work is that he asked what the number was for. Use the dimensions you're given; keep that question.
What to avoid
Don't hand over a single figure with no workings. "About 40 cubes" is a guess with a unit attached, and the panel can't see where it went wrong.
Which method of measurement is your BoQ written to, and why should I care?Show the answer guide
Because the same slab gives different billable quantities under different rules. Name the one you have used. If it's RICS NRM 2, know its basics: work is measured net as fixed in position, the extra material for laps, joints and waste is treated as part of that net item rather than added on top, and openings at the boundary of a measured area are always deducted.
On your project the bill may be written to a different standard, or to the project's own preambles. The strong answer says so, and says you read the preambles before you measure anything.
Do you deduct the rebar from the concrete volume?Show the answer guide
Under NRM 2, no: in-situ concrete takes no deduction for reinforcement, or for voids under 0.05 cubic metres (troughed and coffered slabs aside). Other rules can differ, so name the one you are quoting.
Your BoQ says 400 cubic metres. Site poured 460. Who pays for the 60?Show the answer guide
It depends on the contract, and the panel wants to hear that before anything else. On a remeasured contract the contractor is paid for what was actually built at the bill rates, so the quantity moves. On a lump sum the contractor generally carries quantity risk within the defined scope.
Then ask why it grew. If the drawings changed, that's a variation, not a measurement error, and it is priced differently. And either way the executed figure stands on joint measurement records signed with the consultant, not on your take-off alone.
What does a BoQ rate actually cover?Show the answer guide
More than the item description. The rate covers what the description says plus whatever the preambles and the method of measurement deem included: formwork, extra excavation, testing, depending on the bill. Read the item alone and you will either claim formwork twice or lose it once.
What's a provisional sum?Show the answer guide
Money in the bill for work that couldn't be defined at tender. It's spent only on instruction and as the contract says. Treat it as a placeholder, never as margin.
Shop drawings, submittals and RFIs
Entry – mid
On a consultant-led project, almost nothing gets built until the consultant has stamped the paper for it, and the technical office is the department that carries the paper there and back. Graduates and experienced engineers both get these; what changes is how far you take the answer.
Nobody here will ask you to define a shop drawing against an as-built. They assume you know, and ask what comes next.
How do you turn design drawings into shop drawings? What do you actually add?Show the answer guide
"More detail" is the answer that fails. The interviewer wants to hear what the detail is.
For a concrete frame: full setting-out dimensions site can mark from; reinforcement detailed with cut lengths, laps and where the laps fall; openings and sleeves taken from the coordinated MEP drawings; levels; and the RFI numbers that resolved any clash on that sheet. In the title block, the drawing number, the revision, and the design drawing it was developed from.
Then the line that marks you as safe: a shop drawing does not change the design. If something has to change — a bar size, a level — that goes through an RFI or a proposal and gets approved first. It does not get slipped into the shop drawing in the hope nobody notices.
One candidate's version
On a school job I was detailing a roof slab and the HVAC layout had a 600 mm duct running straight through a beam. I didn't draw the opening. I raised an RFI with a section through it, and the designer dropped the duct below the beam about a week later. If I'd just shown the hole on the shop drawing, I think it would have been approved without anyone noticing, and we'd have poured a beam with a hole through the middle of it.
The point of the story is the line between what the technical office adds and what the designer decides. Bring a case of your own that shows the same line.
How do you control drawing revisions?Show the answer guide
A fixed numbering system that carries the project, discipline and drawing type; a revision index that moves with every issue; clouds around what changed and a line in the revision table saying what and why.
Then the bit candidates skip: what happens to the old revision. It gets stamped superseded and pulled back from site against a transmittal. Issuing the new one is not enough. The superseded drawing still sitting in a subcontractor's drawer is the one that gets built from.
The consultant returned your drawing as "revise and resubmit". What now?Show the answer guide
First, know what the status means on this project. Consultants commonly use lettered codes — approved, approved as noted, revise and resubmit, sometimes rejected — but the project's submittal procedure defines them, not habit. Say that before anything else.
Then: answer every comment in a comment-response sheet (done, or not done and why), and resubmit at the next revision. And the part that matters on site: nothing gets built off a revise-and-resubmit drawing, including the bits the consultant didn't comment on.
What goes into a material submittal?Show the answer guide
Manufacturer's data sheets, test certificates, samples where the spec asks for them, supplier details. The document that makes the difference is the compliance statement: the specification taken clause by clause, with what the product offers set against each one, compliant or not, and a page reference into the data sheet.
Fill the non-compliant column honestly. The consultant will find the deviation either way; the only question is whether they find it in your table or find it themselves and stop trusting your next submittal.
The specified product isn't available. What do you do?Show the answer guide
This tells the interviewer whether you understand the specification is part of the contract.
Prove the unavailability on paper: a letter from the supplier or a written lead time. Raise a substitution request with a clause-by-clause comparison of the specified product and the proposed one, plus the effect on cost and programme. Order nothing until it is approved.
Then the money question, which lifts a mid-level answer: if the substitute is cheaper, who keeps the saving? The contract decides, and it may be handled as a variation. Raising that unprompted sounds like someone who has sat in a commercial meeting.
One candidate's version
We had a roof waterproofing membrane specified by brand and the agent quoted ten weeks. I got the lead time in writing and submitted two alternatives with a comparison against the spec clauses. The consultant rejected the first because the membrane was thinner, and approved the second after a sample and a test. We lost three weeks instead of ten, and the price difference went through as an omission.
Notice the rejection stays in the story. Swap in your own material and numbers.
What to avoid
Avoid "we found an equivalent and used it". The word "used" is the problem: it means site installed something the consultant never approved.
Method statements, ITPs, hold and witness pointsShow the answer guide
Three questions that arrive separately and share one answer: what's a method statement, what's an ITP, and what's the difference between a hold point and a witness point.
The method statement says how the work will be done: sequence, plant, labour, safety measures, who is responsible. The inspection and test plan says what gets checked, when, by whom, and against what acceptance criteria. The ITP is where the method turns into signatures.
At a hold point work stops until the consultant attends and signs. At a witness point they are notified, and if they don't turn up at the agreed time, work carries on. Mix those two up and you have told the panel you have never waited for an inspector.
These two drawings conflict. Write me an RFI.Show the answer guide
A live test in some interviews, sometimes with two printed sheets in front of you. They are not marking your English. They are checking whether the consultant could answer what you wrote.
A good RFI asks one question, not three. It gives exact references (drawing number and revision, grid, level, spec clause), describes the conflict without interpreting it, proposes a solution so the consultant can reply "agreed", and states a required-by date with the reason for it — "slab formwork starts Monday".
Write it in that order in front of them and say why the proposal is there: consultants answer a proposal faster than an open question.
One candidate's version
RFI 047. Beam B12 soffit level: structural S-204 rev 2 shows +3.60; architectural A-310 rev 1 shows the ceiling at +3.50. Please confirm. Proposal: keep the structural level and drop the ceiling to +3.45, below the beam. Response needed by Sunday; deck formwork starts Monday.
The numbers are illustrative. What matters is that every word can be checked against a drawing.
How do you chase RFIs that have gone overdue?Show the answer guide
An RFI log with sent date, required-by date, age in days, status, and the programme activity waiting on it. Then a written reminder, then the overdue items tabled at the progress meeting and minuted.
And the sentence they want: site does not build ahead of an answer because "they'll obviously agree". If site does, the technical office will be asked why it didn't stop them.
Interim valuations and variations
Mid – senior
This is where someone who has done take-offs separates from someone who has run a monthly valuation. Experienced candidates get these in depth; graduates often get one, to see whether they understand where all the paper ends up.
The general civil engineer page asks how you handle a change order. This set asks what happens around it: how you spot one, how you price it, how it lands in the valuation.
Talk me through preparing the monthly interim payment application.Show the answer guide
Describe the structure. It's cumulative: for each item, quantity executed to date, less what was certified previously, gives this period. Add materials on site if the contract allows it. Then deductions: advance payment recovery, retention, anything else agreed.
Then the supporting documents, which is where experience shows: signed measurement records and approved inspection requests, because work that hasn't been inspected and accepted doesn't get certified. Under FIDIC's 2017 Red Book, the Engineer measures the works and issues the payment certificates, and if they withhold an amount from an interim certificate they have to give reasons and show the calculation. In practice that means a good application leaves them nothing to withhold.
And before you submit, ask whether one disputed item could hold up the rest. If it could, split it out.
One candidate's version
On a residential block we ran the valuation off an Excel model linked to the take-off. One month the consultant held back the whole plastering item because inspection requests for two floors were still open. After that, a week before every submission I pulled a list of every quantity without an approved IR and sent it to site to close out.
It doesn't claim a perfect valuation; it says what one withholding taught them. Use the same shape for yours.
How do you check a subcontractor's payment application?Show the answer guide
Three comparisons. Their quantities against what was measured and accepted. Their rates against their subcontract, not your main contract. And what they're claiming against what you claimed for the same work. If they're asking for quantities your client hasn't paid you for yet, find out why.
Then their deductions: advance, retention, and back-charges for anything the company paid on their behalf. Back-charges need paper at the time, not a list assembled at final account.
A new revision of a drawing lands. How do you tell whether there's a variation in it?Show the answer guide
Don't trust the clouds. Things change without one.
Overlay the new revision on the old one — in AutoCAD if you can — re-measure what moved and compare it with the bill and the contract scope. A change in quantity, quality, scope or sequence is what makes it a variation. Then price it and put it in writing before site starts.
The panel is deciding whether you'll protect the company or let changes slide through quietly. A specific example answers that better than any principle.
One candidate's version
Structural rev 4 came in with one cloud on a single detail. I overlaid it on rev 3 and found the beam bars on a whole floor had gone from 16 to 20 mm with no cloud at all. I measured the difference, about six tonnes, and we sent notice before the steel fixers started on that floor. The consultant's first response was that it was a correction, not a change. After a meeting it was recorded as a variation.
Revision number, bar size, tonnage, timing of the notice: all checkable. That's what makes it land.
There's no rate in the bill for this new item. How do you price it?Show the answer guide
The usual ladder: the bill rate if one applies, then a similar item adjusted for the difference, then a new rate built from scratch. Your contract sets which ladder is binding.
A built-up rate comes from components: materials from quotations, labour from productivity, plant, then overheads and profit. Say where each number came from. A rate analysis with no source for its productivity gets bounced on first review.
The Engineer's instruction is really a variation, but it doesn't say so. What do you do?Show the answer guide
Under FIDIC 2017, the contractor gives the Engineer notice immediately, and before starting the work, that it considers the instruction a variation; the Engineer then has seven days to respond. Your contract may differ, so say which form you're quoting.
The principle travels to any form: notice comes before execution, not after. Building first and arguing later turns a variation into a claim, and a claim is a much harder thing to get paid.
Coordination, document control and the programme
Entry – mid
Technical office engineers are not usually planners, but they get asked about the programme to the extent it touches their work: when a submittal has to be approved so procurement doesn't slip.
How do you catch MEP clashes with the structure before they reach site?Show the answer guide
On a lot of jobs it's combined services drawings: electrical, HVAC and plumbing laid over the structure on one sheet, with openings and sleeves checked with the structural designer before the pour.
Where the project runs a BIM model, clash detection is done in software — Navisworks' Clash Detective, for instance — and each clash is assigned to someone to resolve. Mention it if you've used it; if you haven't, say you know the idea. Clash detection doesn't fix anything. It gives you a list, and the fix is a coordination meeting.
What's a transmittal for, if you've already emailed the drawing?Show the answer guide
A numbered record of what was issued, at which revision, to whom, when, and for what purpose: approval, information, construction. A year later, when someone asks when you received revision 3, the transmittal answers it, not anyone's memory.
Email moves the file. It isn't the record. Say where the record lives on your project, whether that's a document management system or a strictly numbered folder.
When do as-built drawings start, and where does the information come from?Show the answer guide
On day one of construction. Site red-lines changes on a marked-up set as they happen, and the technical office picks them up regularly. Anyone who draws as-builts from memory in the last month hands over drawings nobody believes.
They aren't a formality either: handing them over is often tied to taking-over or the final payment, depending on the contract.
What's the difference between a baseline and an update in Primavera P6?Show the answer guide
The baseline is a complete copy of the approved programme, saved before the first update, which progress gets compared against. The update is the live schedule where actual dates and percent complete go in each period. Comparing the two tells you whether you're late, and where.
Connect it to your desk: your submittal log should know which programme activity each submittal feeds. That turns a consultant's late reply into a number of days instead of a complaint.
We'll test you on AutoCAD and Excel. What should you expect?Show the answer guide
AutoCAD: open a drawing and pull an area off it with a polyline, handle layers and xrefs without getting lost, measure at the right scale. Excel: a tidy take-off sheet, formulas rather than typed-in results, a conditional sum by item. Typing a result into a cell by hand costs you marks even when the number is right.
If Revit or P6 is on your CV, expect a practical question on those too. Separate what you've used on a live project from what you did on a course.
The scenarios that decide it
Mid – senior
The technical office manager asks these because they happened to them. None has a perfect answer. What they want to see is that you know who to write to, when, and what you tell site in the meantime.
The consultant has been sitting on a submittal for four weeks and site is waiting on it.Show the answer guide
The trap is that it invites you to complain about the consultant. Don't. Describe what you did.
Weak:
I kept calling the consultant every day and followed up until they finally responded.
No paper, no dates, no programme impact. If the delay turns into a claim, there is nothing in that story anyone could submit.
Strong:
It was the fire pump submittal, eight weeks' delivery. Two weeks past the review period in the submittal procedure I sent a written reminder, tabled it at the progress meeting so it was minuted, and asked the planner to show the impact on the programme. Meanwhile I got the supplier to hold a production slot without a purchase order. Approval came after five weeks, and the impact was on record in days.
Dates, documents, a measured impact, and something done to limit the damage without breaking procedure. That's what protects the company.
The rule under both: a follow-up that leaves no written trace didn't happen, contractually at least.
Site built something before its drawing was approved. What do you do?Show the answer guide
Don't start with who's to blame. Start with what was built: does it match the submitted drawing, and are comments likely? Tell your manager in writing, and decide with them whether to notify the consultant now or push the approval through — but don't hide it, because the consultant will find it at inspection.
Then fix the cause. Why didn't site know the drawing wasn't approved? If unapproved drawings were within their reach, that's a technical office problem before it's a site one.
You realise you overstated a quantity in last month's valuation. What happens next?Show the answer guide
An integrity question dressed as a technical one. The only acceptable answer is that you correct it; how you do it is what's being scored.
Tell your manager first, with the figure and the cause. Correct it in the next application — valuations are cumulative, so the correction shows as a clear reduction, not a quiet edit. Then say what you changed so it doesn't recur: a second check, or tying the take-off to signed measurement records.
One candidate's version
In valuation 9 I found I'd measured the blockwork for a whole floor twice — the sheet had two copies of the same level. Roughly 300 square metres. I told my manager that afternoon, and we corrected it in valuation 10 as a visible deduction with a covering note. The consultant didn't comment. Since then I reconcile total areas against the drawings before every submission.
What makes it credible is that the figure is stated and the mistake is owned. If this exact thing hasn't happened to you, use a real error from a take-off or a schedule in the same shape.
What to avoid
Avoid "I'd leave it, the consultant's QS will pick it up if it matters". That sentence ends the interview.
The consultant's QS won't accept your quantity. How do you handle it?Show the answer guide
Sit down over the take-off, not the total. Ask to see theirs and go line by line: reference, dimensions, deductions. Often the gap is one line — a different measurement rule, or a different drawing revision.
What the take-offs can't settle gets written up and escalated, and split out so it doesn't hold up the rest of the valuation. And keep it impersonal: you will be sitting across from this person every month until the final account.
You have a tender to price in a few days and not enough time. How do you organise it?Show the answer guide
Don't say you'd work late. Say how you'd split it: the items that carry the bulk of the value get measured and priced carefully; small items get rates from previous jobs, adjusted. Supplier and subcontractor enquiries go out on day one, because they're the slowest part.
Then write down your assumptions and exclusions and submit them with the price, and raise every tender query before the query deadline. A price built on an assumption nobody wrote down is a loss waiting for the contract to be signed.
The closing conversation
The part most candidates waste. What you ask here is read as carefully as what you answered.
Questions to ask them
- Does the technical office prepare the valuations here, or is there a separate QS team?
- Who's the consultant, and how long are submittals taking to come back on the current job?
- Is the main contract remeasured or lump sum, and which method of measurement is the bill written to?
- Are you coordinating in a BIM model or on combined services drawings?
- How many engineers are in the technical office, and who reviews my work before it goes out?
The question about submittal turnaround is the one that tells them you know where time disappears in this job.
The two pages every job shares
This guide covers your field. These two cover the frame the questions are built on — the behavioural canon, and the screening call that decides who reaches an interview at all.
- Behavioral interview questionsThe canon every profession shares: error, conflict, pressure, initiative, and where your limits are.www.atshiring.com/en/interview-questions/behavioral
- Screening and first-round questionsThe recruiter call: introductions, the administrative gate, and where people lose money on salary.www.atshiring.com/en/interview-questions/screening
Before the interview
Ordering note
The order is our judgement of how these interviews usually run, not a frequency count: the job first, then the take-off test because it often comes early and graduates face it hardest, then approvals, then money, then the scenarios that tend to close the session. We found no source that measures how often each question is asked for this role, so we don't claim a most-asked order.
Sources
Everything consulted for this page, named in plain text.
- FIDIC — Conditions of Contract for Construction (Red Book), 2nd edition 2017
- Fenwick Elliott — The role of the Engineer in FIDIC 2017 contracts (presentation, 3 June 2021)
- RICS — NRM 2: Detailed measurement for building works, 2nd edition, October 2021
- Oracle — Primavera P6 Professional User Guide: Baselines
- Autodesk — Navisworks: Overview of Clash Detective Tool